We are in the process to select two Diesel Generators 2.5 MW, and would like to know what differences are between a generator API-546 and one Nema MG-1.
Essentially, I know that the API-546 test section is more complex than the one at Nema MG-1, but not sure about the area classification and...
We are designing a new Centro control Building at a Refinery.
I would like to know if is there any Standard for the minimum number of doors (access) for a Control Room.
Thanks.
Hello,
I am looking for a free Software or Spreadsheet for Power Electric Network Reliability Calculations.
I know about the Enrico software, but now I have not access to it.
I appreciate any suggestion or comments.
Thanks.
JCS.
Hello,
I am working in a Refinery’s control room and I am looking for a standard or guideline reference for a Formal Electric Load Report, usually I have done that in an Excel Table, but this time I would like to see if I can improve that.
Somebody has any idea or suggestion.
Thanks