Hello,
I am in the process of integrating a project schedule into another main schedule. One task was for 5 days - 11/7 to 11/13. When I pasted the plan into the main schedule it changed to 5 days 11/7 to 11/14. The calendar is the same for both (standard working time). Has anyone ever seen this...