  1. wanstronian

    MS Project increasing duration

    Hi, I know this is an age-old problem/bug/feature of MS Project, but can someone please tell me why allocating resource to a task line in project INCREASES its duration unless the resource is added at 100% utilisation? I have a task with effort of 54 days. I have two resources assigned, one at...
  2. wanstronian

    Duration vs Work

    Hi, Is there any way to set MS Project 2000 such that when you enter an effort, the duration is automatically set depending on the hours per day you've defined in the project settings? For example, we work 7.5 hours per day. I want to be able to enter a task effort of 22.5 hours, and have the...