Has anyone seen the problem of trying to relevel if future task is completed? MS Project will not remove completed tasks from the resource's future workplan.
For example:
Assume all of the following tasks are performed by the same resource.
Task 1: July 1 - July 8
Task 2: July 9 - July 16...