Dear all,
please help me to find a solution to this question.
If We are in the steam blowing phase of BOP and HRSG
and there's no availability of the electrical substation,
it's possible to run the GT in FSNL during several
blowing? Tha gas turbine is a V94.3A2. There's some
problem...