Hi,
I am using MS Project 2003 and trying to do --
1.Create a new project, Add a task, set duration = 1 day
2. Change the task type to Fixed Duration and uncheck "effort driven".
3. change % Complete to 10 %.
4.Assign a resource to task. Now the diff fields will be:
Work = 8 hrs
Actual = 0.8...