  1. dieg0

    How do I wrap the Predecessors field in MS Project ?

    I'm running MS Project 2003. I am working on a project that has many tasks and the predecessors field is VERY long. Is there a way to word-wrap that field so that I could decrease the width of the field, but still view all the tasks? I have tried increasing the height of the row, but I still...
  2. dieg0

    Resouce Names (drop-down list) sorting

    Hi there - Is there a way to sort alphabetically the names under the Resource Names drop down list. I can sort these names under the Resource Sheet, but the names appear unsorted in the Gantt Chart view i'm using MS Project 2003, btw. thanks.