I managed to copy the schedule from one project to another. However, it did not solve my problem.
While in the copy window generated from tools, project utilities, under "To" i changed the planning units to days from hours on the from/ original. However everything is still displayed in hours...
I have been trying to change the 'planning units' in Primavera 3.1 from hours to days. However whenever I try to change or copy from another project via the menus: tools, project utilities, copy, I consistently get a message "invalid project name", eventhough all names and characters match.
I...