Hi,
I'm trying to save my project as an htm file. I am able to create a file that looks exactly the way I want, except the file link that I have in the indicators column is not honored when it is saved as an htm. I think this may be because the format for the column defaults to...
Sometimes, I have a task (sucessor) with one predecessor. The predecessor complete date and the sucessor start date have a huge gap between them, and there's no obvious reason; the sucessor is not part of a summary task with a later date and the sucessor isn't tied to a later task either. The...
I am able to get the text in task" to text wrap; why won't the numbers in the "predecessors" or "successors" wrap also? I'm making the row high enough. thanks...
Whenever the critical path is calculated, it is calculated as the path with no slack that leads to the LAST (latest) task in the file. Is there any way to get the critical path for a task that is not the latest task?
Right now I'm doing it by deleting the later tasks, though I need to remember...