    Setting Planned Finish Date based on Remaining Work

    I am trying to use Actual Work and Remaining Work to adjust the planned Finish date of a task in progress (with an Actual Start date) when resource leveling. However, when I level, project seems to set the planned Finish date based on the Remaining Work from the Actual Start date rather than...