  1. obede

    Resource Calendar

    I'm Newbie on MS Project. The Default calendar is 8h/day but there are resources that need work 10h/day. I changed the resource calendar but I don't get any change on project. How can I aplly the changed resource calendar? Thank you very much Obede Brazil
  2. obede

    Milestone Duration Error

    Hi dear I configured the working time to 8 hrs/day and I created tasks with less than 8 hrs. Why doesn't the milestone duration match the sum of taks? Thank you very much Obede Brazil
  3. obede

    Duration Collumn

    Hi, dear I'm Newbie on MS Project. I need to create a Collumn similar to Duration Collumn but this collumn needs to maintain fixed values, that is, even when I change the values on Duration Collumn or Actual Duration Collumn this Collumn doesn't change values. Is it possible? How can I get it...