Hi,
I have a 3phase 208V 15KVA ups rated for 0.8 p.f. This is an older unit (1994) and the manfacturer was bought out by another company and I am unable to get any support on it.
Does this rating mean I can supply a 0.8 PF load up to 15KVA and a 1.0 PF load up to 12KW? I'm assuming that the...
I'm working on a project in Canada so I am following the CEC guidelines. One of the plants processes that was non-hazardous has been modified and now the area is classified as Class I Zone 2. I have Nema 4X junction boxes containing terminal blocks. According to CEC 18-156(1)(7) boxes, fittings...
Hi,
I posted on this board several months ago and received some good advice. Thought I would give it a try again.
I am currently working as an EE in a plant. My duties involve:
-Control system upgrading/modification. This involves some PLC programming, designing control schematics using ACAD...
I live in Canada and I'm finding it extremely difficult to find an Engineering position. I graduated 2 years ago with a B.Eng and have had 2 short term contracts in that time, that didn't lead anywhere. I've been unemployed for over a year now and things are not getting any better. My field of...