Hello
I should track the progress of some resource, gathering their "Actual Work" to be charged in the "Resource Usage".
As they don't have and/or don't know MS Project, I thought to extract an Execel File just like this View and spread it.
Unfortunately I didn't figured out how to do this: any...
Hello!
quite simple question, but tricky to solve, at least for me.
Create a task with Work = 40 h (=1 week for a person full time).
If you assign one resource 100%, you get 5 days as duration. Fine.
Now try adding a second one, putting both people at 50%: it is one person equivalent, so noting...