I appreciate your help.I'm installing an underground 11kv feeder (2KM long) and two control cables for the inter-trip send and receive signals from Multilin relays. What is the minimum segregation required between the two? I have seen some thing from 150mm to 1500mm? Could someone help please...
Gentlemen, could you please advise the main differences between Metal Clad & Metal Enclosed MV (6.6KV) Switchgear? Which one is better from operation and safety aspects?
Many thanks in advance for your support.
In a project spec, the following statment is stated
"All electrical equipment and instrumentation in outdoor areas and process enclosures/shelters shall, as a minimum, be certified by an internationally recognised body for use within the applicable Area Classification, as defined in API RP 505...