Hi all,
I would like to know the difference between a triangular mesh & an irregular shape mesh in FEA analysis. What are the limitations & advantages between the two approaches?
Thanks
Hi,
I'm constructing a piled retaining wall over a soft ground. The borelog shows the first 30ft is very soft clay with plasticity index of 40 & average SPT of 2. The water table is 1 ft below the existing ground. I will raise the platform level by 4ft with compacted fill. I've referred to...
Hi,
I'm part of a road maintenance crew assigned to carry out a field traffic count for an existing signalized intersection. The last time I was involved in Traffic Engineering was in College. Anyway, the signal phase for each leg is about 20 to 35 seconds. The whole cycle is about 140...
Hi all,
I'm supervising a soil nail wall construction. I need to carry out some design calculation for rearranging the soil nail layout to accomodate the site. I'm using the FHWA manual as reference.
How to assign the Sv & Sh if I were to use staggered layout. Assume the initial layout was...
Hi all,
I've browsed few rock mechanics books such a Hoek et al on shear strength of rock; it would be a great help to me if I can get some ball park figures to start off with before I do a full scale testing. The rock is highly weathered or fragmented. The RQD values of the rock core samples...
Hi all,
I am carryng out routine soil investigation on slopes during slope cutting; the objective is to counter check the design parameter during design stage. Boreholes and test pits are conducted. We were unable to collect undisturbed samples in the borehole. The samples are fractured stiff...
Hi all,
I am carryng out routine soil investigation on slopes during slope cutting; the objective is to counter check the design parameter during design stage. Boreholes and test pits are conducted. We were unable to collect undisturbed samples in the borehole. The samples are fractured stiff...
Hi all,
I'm looking for grout specification for soil nail. My main concern is shrinkage. I checked a few FHWA specs but there is no specification on the grout.
Thanx in advance.
Hi,
I'm a Geoslope Version 4 user & I tried my friend's Geostudio 2004. There are quite a few changes in the 2004 version notably the output files are reduced to one file. I imported a version 4 project to the 2004; the results were okay in Bishop Method but the FOS were way off when I used...
Hi,
A post tensioned girder was poured with cold joints formed &
there is no proper construction joints. The incident happened
when one truck of the concrete was rejected since the slump
was only 2 inch. The next pour was 2 hours later but they claimed
it's okay since set retarders was added...
Hi all,
I'm looking for work examples for superelevation especially on reverse & compound curves for both circular & spiral curves. The curves i'm dealing are pretty 'tight'; the straight section between two curves is very short or non-existing. The radius are ranging from 200 to 600 feet...
Hi all,
I'm designing a portal frame & my client told me to use some steel sections from Australia.
What conversions do I need to do to perform in order for me to use the foreign sections?
Our Ultimate limit state factors is 1.4D + 1.7L & I was told Australia Code is similar to Canadian Code...
Hi,
I posted this thread in AASHTO forum & hope to get some feedback here.
I'm planning to build a short span ramp to allow a 40 foot trailer to climb 10 feet.
Initially, I suggested 2:1 H:V or 50% climb & the reaponse was no. What if I lower the gradient to 3:1 or 4:1 ? The climb would be 33%...
Hi,
I post a similar question before; I hope to get better response after I refine my post. My friend is planning to build a ramp swith 2:1 (H:V) slope. The ramp is 20 ft run & 10 ft rise. I'm looking for charts or publications to check if a fully loaded 40 ft container truck can actually climb...
Hi all,
I'm looking for SPT N correlation to phi for rocks. The samples I collected ranges from very dense sand, shale & rocks with SPT N 50. Is there any reference online I can refer to ? Bowles has a pretty good correlation table for sand up to SPT 45.
Thanks in advance
hi all,
Can someone shed some light on embankment filling on sloped ground?
What's the steepest allowable natural slope a 2:1(h:v) embankment can be constructed on top assuming no slope stability & bearing problem to the natural slope. In another words, the gradient which machinery can perform...
Hi,
I'm designing a carpark basement of a office tower. the basement is 3 ft below mean sea level & the water level recorded in the piezometer is roughly the same level. I'd appreciate if someone can shed some light on how to to ensure the basement is not subject to flood.
th
thanks
Hi,
I've assigned borehole on site to collect soil samples & data for slope design.
Unfortunately, I'm getting disturbed samples since the formation is very stiff sand to sandstone of SPT 50. What other tests should I assign?
In fact, is there a rule of thumb in soil test assignment for slope...