When coordinating a feeder fuse in a switchgear line up with upstream main or substation breaker, would you coordinate the fuse with phase or ground element of the breaker?Thanks
I work in maintenance department of a manufacturing company. We intend to change the hv fuses inside an arc resistant switchgear and install a fix-mounted breaker. Can we validate that the switchgear stays as arc resistant considering the construction of the switchgear will not change?
Thanks