A number of years ago we installed a basic Eaton ATC-600 IQ Transfer Controller in an older GE 5kV line up. The customer wanted Option 29J (Manual Transfer Back to Normal rather than the standard Automatic return.) The option was installed via a Option Feature Module via serial port. The...
I am looking for a detailed written procedure on how to perform an AC Hipotential test on a newly rewound medium voltage generator. If anyone has a generic procedure or can point me in the right direction it would be appreciated.
Thank you.
I was asked a question today. I thought I knew the answer and replied as best I could. I wanted back up and have been looking for that back up all day. The question involves new standard 15kV Metal-Clad vacuum switchgear manufactured in the US.
"When landing properly terminated 15kV cables on...