Happy Friday Engineers,
would anyone be able to share a Short Circuit Calculation - Point to Point Method excel spread sheet? or know of a software that does this via pt. to pt. method?
I have a situation where there is an existing 800a fused switch feeding a new 1200a switchboard with 3 sets of 4#600kcmil + grd. I cant seem to find the code violation for that, any thoughts?
All,
I have a situation and I need to know NEC cite sections of the code.
if I have 5 different electrical services can I commingle downstream in a crown box cables/feeders from the different services? see picture attached herewith please help
I HAVE TWO 480V CONDENSERS FED OFF ONE 60A MCB IS THIS CODE COMPLIANT? (THEY BOTH HAVE DISCONNECTS IN LINE OF SITE)
12 Ton Unit
MOP – 40A
MCA – 26.4A
14 Ton Unit
MOP – 40A
MCA – 31.3A
Scenario: 2 rooms one room housing ATS sw's other room housing Transformers and secondary fused disconnects for the ATS conductor protection. Can these Fused discos be in a separate room per NEC?