Dear techies, I have attached a pic of commercial sewer drainage line. Here the designer put Inspection chambers at every joint or junction. He put chambers at even 1.5mts distance which is just weird.
I don't think this as proper way. If we keep adding IC at every joint and junction the whole...
Dear friends, i was looking to clarify the difference between FCO and Manhole. I have done some study and read threads here but info is contradicting.
1.Look into the file attached where ground floor sewer line is depicted which utilises manhole at every point. I have been designing such models...
Dear Engineers, I have an issue to discuss. A customer approached me yesterday to get an engineering help regarding his problem.
His building consists of basement and three floors above it. Previously I suggested him to have a pump at the basement to pump up the three toilets waste to ground...