Hi All,
I'm faced with a little issue and i'm really hoping you guys will enlighten me.
I've designed and routed an underground water pipe system (fire ring main) for a gas handling facility. A 10" header at 600mm from top of pipe to the finished ground level, distributes water to all the...
Hi everyone,
I've been going through some Caesar II model to profound solution(s) to the failing pipe.
Going through most of the existing models I noticed that an anchor type restraint was placed in-between connecting weld neck flanges. This was repetitive in all the models I checked.
Generally...
Hi,
Generally my idea of a jacketed piping system is one protected by an insulating cover. Typically used for the transportation of hot steam or hot water, a jacketed pipe maintains the temperature of the material flowing through it. The jacketed pipe used in large pipelines prevents the harsh...
Hi,
Im a mechanical/piping engineer, and im used to ASME sec VIII div1 for design.
Ive been asked however, to design a diesel storage tank, using "EN 12285-2".
Ive got no idea what-so-ever where to start from, as all my previous vessel designs have been based on ASME sec VII div 1.
Help urgently...