We are using an automatic closing system in 132/33kV substation, where we have 4 nos. of 132/33kV transformers which runs in 2 groups. T1||T2 and T3||T4.
Scheme is such that if one transformer trips, the left alone transformer from that group get paralleled with the other healthy group of...