  1. Windows83

    MS Project 2010 Change working time

    I am using MS Project 2010 to create a construction schedule based on a 9 days on, 5 days off shift. How do I change the working time to reflect this? I can do it manually but don't want to input two excepetions for each month of the project. Is there an easier way?