The Project start date is greyed-out and cannot be changed. I can change the start date of the first task but that simply makes the project longer; it does not move the whole project. What am I missing?
Hi,
Is it possible (and if yes - how?) to move the whole schedule in MS Project without changing durations of any tasks. Let's say we create a project that would end on December 15 and it would take 6 weeks to complete all of its tasks (often linked). Now we want to move the completion date to...