Thanks for the input. To clarify, the backfill serves as a subbase for a 4 in concrete walkway. The contractor is backfilling at 8" lifts. Logically, would it not be safe to assume to achieve 95% on top foot compacted at 8" lift, you would have 95% at the lower layers? So the frequency is a...