    Discovered Cold Joint after the fact in Monolithic Slab for a Metal Building in a High Velocity Wind

    What obligation does the EOR have if the original contractor did not follow his plan? Is the engineer not obligated if the contractor did not follow his design and this is one year later? What else can be done to rectify this horror?
  2. NeedanewGC

    Discovered Cold Joint after the fact in Monolithic Slab for a Metal Building in a High Velocity Wind

    I recently was reviewing photographs of a structure that was constructed and became aware that the general contactor intentionally poured a cold joint in the monolithic slab foundation for a metal building. The project is located in a high velocity wind zone and the thickened edge of the mono...