Yup. Some locations were nailed. I think it's okay.
however, some portions were not nailed and the cut is almost 80 degree, the retaining wall is 1m behind the cut. That's my concern. The retaining wall may be up to 3-4m.
Here is my situation:
Our project is building some resort on hillside.
we need to build RC wall along the road to fit the entrance of resort. However, the slope is cut so steep for excavation of resort. Bearing capacity is not good enough to build a retaining wall. What i should do and how can...