Thanks to all of you for your great thoughts. Here's what I'm going to do.
10 Pound a rebar inside the square tubing and into the ground for another 2' beyond the foundation and then pour concrete in the tubing with the rebar in side all the way to the top of tubing.
2) Also, there is a 4"...
I'm trying to calculate the deflection of a square tubing post supporting a steel gate. I'm trying to determine the deflection at the top of the post-the free end. Here are the details:
The carbon steel square tubing post is 2"x4"-1/8" wall thickness and 6 feet tall. A continuous hinge will...