  1. khkw

    Wet well and lift station structure for a force main/sewer line

    I am trying to do a fee schedule/estimate for the structural design of a wet well and lift station structure for a sewer line. Any suggestions for the hours of the engineer and CAD designer? Thanks.
  2. khkw

    Sign and seal a letter for permit purpose w/o firm number

    It is an elevated timber deck about 8' above ground with structural elements. Also with about 3' overhang. City inspector came to inspect and requested the letter.
  3. khkw

    Sign and seal a letter for permit purpose w/o firm number

    I have been asked by a friend to inspect their deck construction in the back of their house. After the construction was completed the city ask them to provide a document (a letter) signed and sealed by a PE to certify that the deck was constructed in accordance with applicable building code. I...
  4. khkw

    Reinforced Concrete Hydraulic Structures.

    I understood that for flexure members, ACI350 requires 1.3 to be applied to the ACI318 factored load. Now reading the latest ACI350-06, I realized that the modification of the factored load for flexure design is even more - according ACI350-06, Sd, the environemtal durability should be applied...
  5. khkw

    Reinforced Concrete Hydraulic Structures.

    Thanks for you help! I was able to get hold a copy of the Bureau of Reclamation "Moments and Reactions for Rectangular Plates." Let me take one step back - These structures are for a dry detention pond, which is designed to detain the storm water run off for some minimum time (24 hours). The...
  6. khkw

    Reinforced Concrete Hydraulic Structures.

    I am in the process of designing a splitter wall (7' concrete spread footing wall)and a filtration chamber (11'L interior X 4'W interior X 12'H open top concrete box which is subject to soil on one side and water on 3 sides)for a detention pond. Q1. According to the publication "Strength Design...
  7. khkw

    Circular tie details for drilled piers

    On the plans I have given the options of splicing or hooks for the ties. I will be checking with manufactures and figure out what is the most constructible and go from there. I agree that #4 or #5 spirals and inner layer or lateral spannings will be the next thing to do if manufactures do not...
  8. khkw

    Circular tie details for drilled piers

    Thanks! Hokie66, Out of the 9" to 10" hook length half is bent and half is straight in the section. It may not be as bad as it sounds. I will check details of ties with the reinforcing supply. Teguci, As far as the location of the max moment and shear -according to the geotech analysis...
  9. khkw

    Circular tie details for drilled piers

    Thanks! It was my confusion. I had that splice length on my mind! What is the standard hook length for this 135 degree bend between two legs of the tie? My vertical bar spacing is 3.5"......
  10. khkw

    Circular tie details for drilled piers

    Thanks for all your responses! JedClampett and JAE both have very good points. But I think introducing #6 or #7's spanning across the interior of the piers might jack up the cost more than they wanted. Hokie66's idea is refreshing but how do you achieve the splice length (36") with 135 degree...
  11. khkw

    Circular tie details for drilled piers

    fc'is 4000psi. Anything above that will have special requirement by ACI318. These shafts are one of the many sections of shafts along the river emankment. The clients wanted use same diameter shafts (36") and similar details....same strength of concrete...therefore to cut their cost. They...
  12. khkw

    Circular tie details for drilled piers

    Shear (500 kips factored)is too high for spirals - size of spirals are limited to #5 unless you go with special heavy equipment. I can not size up the shaft either. It seems the only option is #6 ties.
  13. khkw

    Circular tie details for drilled piers

    I have two concerns about the circular ties (#6) for my drilled piers (for river embankment stabilization, under mostly large bending and shear, minimum axial, 36"dia, 24#11 with #6 ties @ 3"-4" spa) 1. The lap length - is 48 db sufficient (36" as lap length)? 2. the lap details - should the...