Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. Robbiee

    Diaphragm chord design with cold-formed steel (CFS)

    Thanks KootK, On the last point, I ruled out the HSS as an option for this building because it can be done with the tracks. It sounds like you understood that I considered money over the "proper and safe design". That is definitely not the case.
  2. Robbiee

    Diaphragm chord design with cold-formed steel (CFS)

    Thanks. For the track to work as a beam in this building, the hollow core slab needs to bend between the 16" spaced studs. The track doesn't work as a beam here. The proper analysis, in my opinion, is that the edge of the slab is supported on point loads, being the studs. The composite behavior...
  3. Robbiee

    Diaphragm chord design with cold-formed steel (CFS)

    It could. But is it a good idea cost wise? I don't think so.
  4. Robbiee

    Diaphragm chord design with cold-formed steel (CFS)

    Hello all, Looking to see what works better in terms of the design of a diaphragm chord in a building constructed with hollow-core slabs, CFS stud walls as load bearing walls and cast-in-place concrete shear walls. The two options I am thinking of are: 1- CFS straps at the edges of the slabs...
  5. Robbiee

    About selling a "one-man-show" business

    Thanks! all for the responses. @sparweb: Your storey happened to me almost exactly before I started on my own. But, as I said, my "firm" is only me as an engineer. My employee can't replace me. @ Littelnch: I don't look for work. It comes to me from few repeated client. I kept it this way...
  6. Robbiee

    About selling a "one-man-show" business

    Thanks! phamENG. I don't see working with a partner or a boss for a couple of year that big a deal, especially that we know that I am staying for them. In fact, I think I would like to stick around for some time after just to gradually adjust everything.
  7. Robbiee

    About selling a "one-man-show" business

    Hello, Can a firm with one engineer and one CAD person be sold? I was thinking, since getting closer to the end, let's see what others say.
  8. Robbiee

    New slopes for suspended parking slab

    dik, Agree, but adding loads means increasing punching shear and loads on columns and footings, which might not work. That is why we are trying to stick to a repair that is within the capacity of the structure.
  9. Robbiee

    New slopes for suspended parking slab

    Foam concrete weighing half of weight of gravel might work subject to the approval of civil and building science engineers. Raising the slab on one end? Can't add enough concrete to achieve the slopes. Adding composite topping is beyond the scope of this job.
  10. Robbiee

    New slopes for suspended parking slab

    Thanks dik. I just emailed a supplier of foam concrete in my area and will see their input.
  11. Robbiee

    New slopes for suspended parking slab

    Thanks HTURKAK. Will check our market if something similar is available.
  12. Robbiee

    New slopes for suspended parking slab

    Thanks dik I was thinking of using the allowance for the 4" gravel for new light weight fill, insulation or lightweight granular.
  13. Robbiee

    New slopes for suspended parking slab

    Hi all, We have an existing suspended two-way concrete parking deck slab that needs the surface slopes increase. The slab design loads are fixed and can't go over them. The design includes 4" of asphalt and max. 4" of gravel. However, to achieve the required slopes, we need up to 12" of gravel...
  14. Robbiee

    Trying to avoid expansion joint

    Dik, I am asking if the horizontal EJ in the slab needs to turn vertically into the basement walls down to the footing? Since the basement walls will not experience significant thermal change, is it not adequate to provide control joints to control shrinkage cracks?
  15. Robbiee

    Trying to avoid expansion joint

    Thanks for the input. The underground parking area is fully buried with shafts. Does the EJ need to continue down in the walls? I am hoping to avoid that by having a control joint lining up with EJ in the slab. I have seen many times, where the EJ not continuous into the walls, the walls crack...
  16. Robbiee

    Trying to avoid expansion joint

    Hello, We have a site where we will build 130mx80 one level underground basement/parking garage. There are two concrete 6-storey buildings above the basement that will occupy part of the footprint of the basement and the rest will be used as surface parking area and roads. Please see attached...
  17. Robbiee

    Cracked walls in a parking garage

    Hi all, Looked at a parking garage where two walls were cracked at a couple of locations. The attached images show these cracks. It was clear to me that the cracks happened because the expansion joint in the roof deck was not continued into the walls. Now to repair, I am suggesting to create...
  18. Robbiee

    Strut and tie - fanning strut within kern distance of pier

    Devolving rebars into a pier using epoxy to resist 300kips is questionable, I think! With the spacing and the edge distance reduction factors, it could be impossible, unless your beam and piers are really wide. I wonder why you are not bringing the beam down to the footing! do you need the full...
  19. Robbiee

    Jack-post like column

    Thanks all, We will do a bit more digging and if I find anything useful, I will share it.

Part and Inventory Search