RobsVette,
i totally agree with you as i just wanted to get a second opinion about my justification to my team. i also think that it is not totally stagnant as water is being evaporated as well as refilled on top of the difference in piping configuration to create a flow in between. another...
I am planning to relocate the cooling tower blowdown line of our existing system. I believe that the current installation is not the best industry practice in terms of design and operations as it is connected on top of the pipe instead of the bottom of the pipe. In addition to that, the blowdown...
Hi cry22. Yes, that is correct. There was a recommendation from the water treatment supplier to connect the equalizing line to the supply line to promote flow and eliminate water stagnant on the equalizing line. The existing equalizing line is mild steel pipe.
Hi guys,
I wanted to get some help to check if connecting the cooling tower equalizing line to the supply line (cooling tower outgoing) will have significant effect on the system in terms of flow. The reason for this is that the water treatment vendor suggest that the equalizing line is...