    B31.3 Vent spool hydo test required?

    For a piping in gas service(B31.3 standard), there is a vent spool that includes a valve and a piece of pipe with 2 elbows and is open to atmosphere. Is is required to hydrostaticaly test this spool? If any answer, please tell me the reference.
  2. zigiz

    Material B 58 Grade A ????

    Does anyone know about this material: B 58 Grade A It is used in a pressure vessel for a semi-elipse head whereas shell is A106B. It's manufactured in 1970s. Thanks
  3. zigiz

    WPS

    We have a qualified WPS for pipe to pipe welding joint: material API 5L-X53 to 5L-X60. Does this qualification cover pipe to pipe material API 5L-X52? Please refer to the reference standard article. Thanks
  4. zigiz

    Welding Electrode Lincoln LH DH-80

    Is there any other equivalent welding electrode for "Pipeliner Lincoln LH-D80" ?
  5. zigiz

    Pig Receiver

    For modification on a Pig Receiver in a gas pipeline 10Mpa and for safety case, I need to design a by pass line to vent the traped gas for minor barrel before and after pig in pig receiver. Does anyone know any general info?
  6. zigiz

    Pig Receiver

    For modification on a Pig Receiver in a gas pipeline 10Mpa and for safty case, I need to design a by pass line to vent the traped gas before and after pig in pig receiver. Does anyone know any general info?