Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by x5bulldog

  1. x5bulldog

    ACI 318-19(R22) Ch 26, 26.13 Inspections requirements by the Engineer

    I would like to hear others thoughts on the Inspection requirements by the Licensed Design Engineer(LDP)(or person under the LDP or a qualified inspector) stated in ACI Chapter 26, section 26.13.1.2. Chapter 26 begins with "in the absence of a general building code, concrete construction shall...
  2. x5bulldog

    ACI 351, Machine Foundations: Dimensionless Frequency, ao vs soil parameters

    Question over: Obtaining values or Expanding Tables with comparison to dimensionless frequencies, ao Can anyone point me to references that have published values or how to calculate soil parameters when the dimensionless frequency a0 is outside of 2, 4, or even 10? Most of the resources I find...
  3. x5bulldog

    Excessively oversized drilled or cored holes for post-installed anchors

    I would like to hear what the typical approach/solution is for when construction fouls-up and creates an excessively oversized hole for post-installed anchors. Let's say the hole is oversized by 3 times the anchor diameter or even 4*dia -6*dia. I am aware Hilti addresses oversized holes for...
  4. x5bulldog

    High Pressure Active Water Leak due to Groundwater in Concrete Sump Pit

    Thanks for the help on how to approach this. Does anyone have past experience with injections of polyurethane foam? Drill & Penetrate the wall through the interior, below the horizontal joint and then inject foam to create a curtain barrier. The foam when injected and reaches the exterior, it...
  5. x5bulldog

    High Pressure Active Water Leak due to Groundwater in Concrete Sump Pit

    I have a underground precast concrete sump pit that is actively leaking at a(horizontal)construction joint. The leak is due to the groundwater penetrating the joint. The leak is located about 10 feet below grade, in the corner of the wall, at the joint. Due to the high groundwater table, the...
  6. x5bulldog

    Monolthic Pour at Concrete elevation Change??

    I want to avoid having a construction joint at the interface of a 4'x10'x3'deep concrete pedestal / pads on a mat foundation. Vibratory equipment is going to bear on the concrete pedestals. Can the field / construction guys easily form and pour concrete in this area to get a monolithic pour...
  7. x5bulldog

    Reinforcement for Large Concrete Columns

    Thanks again for all the help! I found what I was looking for. I switched to bridges(even though I am not designing a bridge) and began looking at reinforcement layout for Single-Column Piers since a lot of them are made-up of large dimensions.
  8. x5bulldog

    Reinforcement for Large Concrete Columns

    Can anyone point me in the direction for reinforcing large concrete columms. I want to see typical longitudinal reinforcement arrangement for columns on the size of 10ftx10ft. Is it required to add additional steel away from the perimeter? Also when adding lateral support to some of the...
  9. x5bulldog

    Opening In Existing Structure with temporary bracing, question about steel seismic detailing

    Thanks, I have that publication. Guess I was thinking too much about seismic and seismic detailing of permanent structures :)
  10. x5bulldog

    Opening In Existing Structure with temporary bracing, question about steel seismic detailing

    When designing temporary vertical bracing connections, is the Steel Seismic Design Manual for seismic detailing of connections need to be followed? I want to avoid beef-up gussets, welds, bolts and adding web stiffeners for temporary bracing that will be up no longer thant four weeks. I'm just...
  11. x5bulldog

    Footings on Piles / Minimum shear Reinforcing

    I have read the post "Minimum shear reinforcement in pile caps?" posted on 1 APR 2012. From reading posts, most prefer designing pile caps using the strut-and-tie model. Which is pretty basic for 2-pile, 4-pile arrangements or pretty much symmetric layouts. But at the same time there is CRSI...
  12. x5bulldog

    Using Strut-&-Tie method on a circular cross-section

    Just A concrete pile fully embedded in the ground with a top lateral shear force acting with the top 6 inches of the pile. I am using a Pile Software which we are able to get lateral displacement graphs as wells as shear / moment diagrams and well as some other graphs and results. The IBC has...
  13. x5bulldog

    Steel Pipe Rack Design (mixing mechanical engineer loads with structural engineer loads)

    Thanks for the help, I have the latest ASCE Wind loads on Petroleum Facilities and mentions Pipe Racks, and it discusses 10% of the tributary. Also I have seen the 40psf load from the Process Industry Standards PIP STC01015. This article is about thirty one pages and does not cover alot.
  14. x5bulldog

    Using Strut-&-Tie method on a circular cross-section

    ACI 318 chapter 11 shear design is a littler clearer for circular cross sections. Can anyone point me to the right direction if I wanted to design a circular cross section for shear using the Strut-and-Tie method.

Part and Inventory Search