Gabriel,
Thanks for your feedback. I appreciate knowing that this is the correct path to move down. I am hoping that all checks out.
Strucguy,
I am attaching a plan with the basic condition. I did not want to overload you with all the dimensions if you were just trying to get a general...
I am working on a project that is new construction –CIP concrete, two-way, flat slab. The design accounted for (6) 4” penetrations and (1) 6” penetration placed fairly close together in a column strip. During construction the contractor placed the sleeves for these penetrations in the wrong...