Hi,
I met unknowable situation at the site.
First of all, civil engineer has designed tank foundation with consideration of short-term and long-term settlement.
During the hydro-test, settlement and rebound occurred as 34mm for fully filled tank and 27mm for empty tank after hydro-test.
We tried...