Hi everyone, got a question. I use MS Project to schedule all crafts on a construction site. I need to know if, for example: Task -
Install Recycle Line - (Duration 15 days) I want 6 pipefitters for the first 10 days and then reduce to 3 pipefitters for the remaining 5 days.I cannot figure out...