Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by slushin

  1. slushin

    NFPA 70E Tables Maximum Clearing Time

    So, I know that the tables for NFPA 70E cannot be used if the exact parameters are not met (ie working distance, fault clearing time, max short ckt current, etc). However, I'm confused as to what the meaning of maximum fault clearing time means. Does it mean: 1) the actual maximum time that...
  2. slushin

    Grounding in More than One Location?

    So here's the situation: I have 5 generators paralleled to a paralleling switchgear. The generators are installed outdoors and the switchgear is indoors. The installer grounded the neutral of each generator and also grounded the neutral of the paralleling gear. When I discussed this with the...
  3. slushin

    synchronous motor leading pf

    Can anyone explain theoretically how a synchronous motor can be changed from a lagging to leading power factor? I understand that it can be done by adjusting DC excitation, but I don't understand how a device consisting of resistance and inductance can draw a leading PF.
  4. slushin

    Comm and power separation

    Is the purpose of the separation between communications and power required by NESC 320.B.2 intended to prevent heat transfer from the power conductors to the comm conductors or to prevent induction of voltage from the power conductors onto the comm conductors?
  5. slushin

    120V Phone and Fiber In Same Conduit

    also, the fiber is in a composite cable.
  6. slushin

    120V Phone and Fiber In Same Conduit

    VE1BLL, it is fiberoptic. They are planning on installing innerduct to protect the fiber.
  7. slushin

    120V Phone and Fiber In Same Conduit

    Does anyone know of any standards which state whether or not it is acceptable to run fiberoptic and phone lines in the same conduit? I know what the NEC says, but I'm interested in whether or not this will cause performance issues for the fiber.
  8. slushin

    Universal Vs Multitap Ballast

    Scotty, I might have missed the mark with the way I expressed my question ... Does the universal electronic ballast automatically adjust to the input voltage or does it require setting of taps?
  9. slushin

    Universal Vs Multitap Ballast

    Is there a difference between universal and multitap lighting ballasts? My impression is that a universal ballast will accept many different voltages without physically adjusting anything (ie taps), but that the multitap ballast will require setting the taps on the ballast prior to applying...
  10. slushin

    Two Bonding Jumpers. Should I get rid of one?

    I have a situation where an old switchgear, which used to be the main service for the building, is now downstream from a new switchgear which now serves as the service entry. The new switchgear neutral and ground are bonded as required by NEC. However, the old switchgear still has a bonding...
  11. slushin

    NEC 250.22(5)

    hmmmm ... guess it doesn't make sense to anyone else either ....
  12. slushin

    NEC 250.22(5)

    Does anyone know why NEC 250.22(5) specifically says not to ground the secondary circuit of a pool lighting system? I know that the NEC allows circuits to be ungrounded if interrupting the operation of the circuit would be less harmful than an uplanned interruption of the circuit. This makes...
  13. slushin

    Relevant Work Experience for P.E.?

    Thanks guys. dpc -- I'm in California. The requirement is 4 years of school and 2 years of work experience in this state. They also charge $275 to apply for the P.E. and only refund half if you do not qualify, which is why I figured I would see if anyone had any advice before donating my $137.50.
  14. slushin

    Relevant Work Experience for P.E.?

    Has anyeone come from a manufacturing background and been able to use their time spent in manufacturing towards the 2 years of experience required for your P.E.? I'm an EE and I spent 2 years as a electrical process engineer doing mostly programming, very little design, some design review, and...
  15. slushin

    Calculating Motor Full Load Rating

    Can anyone tell me why the full load amps listed in the NEC do not equal the motor power rating divided by the motor voltage rating? For instance, a 10hp 230V single phase motor is rated at 50Amps according to NEC, but using I=V/P, you get 32Amps.

Part and Inventory Search