Thank you for all the answers... So I talked to the engineer doing the calcs, and he is suggesting to put on the notes to maintain a 95 percent compaction and not disturb the soil. I'm guessing just putting these 2 recommendations are not enough. This foundation is way over designed to...
Hi, the client wants to install a 2.5 diameter, 8 ft deep pile foundation to replace a light pole with an existing 2 ft diameter foundation. What should I put on the drawing for the contractor in terms of removal of existing foundation and putting in the new one? Is there a specific method?