We're looking to help out one of our clients. They have a waterline that is approximately 30" below finished grade. They are requesting a 3"-4" rigid insulation (about an R-3 insulation rating) material to be laid over the top after we excavate down to about 8"-12" above the water line. My...
LHA is right on the money. The meetings, requirements, and hoops you'll have to jump through in PA vary with the municipality you're going to present to. Ideally, you'll look at obtaining a Land Development application for the appropriate county, an NPDES permit, and possibly an Highway...