I'm to prepare a pipe lowering procedure for a 120m long pipe section. i've however hit a snag with the lowering calculation(allowable pipe stresses to be considered) and the lift point spacing. I'm in this situation cos i've always lowered shorter pipe sections and without any written procedure...