    MS Schedule

    I am trying to do the following steps 1. Open MS Project 2. Create a task 3. Make the duration as 1 day 4. Go to the right plane 5. Drag the task to make it for 2 days 6. Now the task duration column shows 1.88 rather than 2 days.Why? Please help.