    @dik Thats not a bad idea. Not my property but I can stop by. I was using blu-beam was tracing the lettering. My rudimentary googling wasnt finding anything useful. Might be a local fabricator thats long gone. Pre-cast piers was my assumption as well.
  2. RickyTickyTavi

    1930's era Beam/Pier House Foundation stones.

    I'm doing a charity project in the city of houston will be doing some minor structural engineering to save these 1930's era homes. Buildings are in really bad shape. I mostly do renovations and repair design for commercial and industrial buildings but I came upon something I had not seen. The...
  3. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 06

    I think you bring up a good point here. There's not really a code rationale for a structural engineer to 'strengthen' the shear capacity of an existing slab/column interface unless the design loads were being changed or the existing capacity was insufficient for the applied loads. Based on the...
  4. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 06

    Compression failure of concrete is typically "explosive". Not like fireball, but the dispersion of energy will send dust and concrete projectiles in all sorts of directions.
  5. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 06

    I think its hard to equate relative movement on the particles once the building starts to move. Is the camera anchored to something and also moving? The vectors the dust takes will have gravity affecting it and whatever force knocked it loose initially. Whether those were localized shear...
  6. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 05

    For what its worth, I've seen a 12" Dia concrete column taken out by a forklift (higher mass, but lower speed than a typical car). Photo from during the repairs. I'm skeptical of the car crash hypothesis in this instance, but there can be some plausibility to that.
  7. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 04

    I get shop drawings for rebar for just about every new construction project I work on. Houston, TX, for what its worth. I would not anticipate this to differ much in the 70s or 80s.
  8. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 03

    Minor clarification of the drawings might be needed, the steel was called out as #4@13. But the notes state that bars shown on the framing plan are top bars, in addition, unless noted otherwise. The top steel, which would be more pertinent to the bending moment for the cantilever was typically...
  9. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 03

    This a distinction between ultimate load and service load in the concrete and steel codes. I didnt make the rules, but the thought process for fall arrest systems are that they are only used once: When someone has an uncontrolled fall off of the building and their harness system catches them...
  10. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 03

    Emphasis mine. This is point were trying to make. 1250 lb load test from an anchor is not a lot of load/weight. To add to this, the 1250 load test loads are typically performed in a manner that cancels out or creates the reactions locally. Insufficient to create catastrophic failures unless...
  11. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 03

    As someone who has designed and observed post installed fall arrest systems on buildings as old as 120 years old and a observed the load test. No. Typically the load test is performed by testing, by tying two anchors together, then jacking them with a load meter until yes, 25 percent of the load...
  12. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 02

    I dont understand the fascination with the fall arrest system(s) being installed, even if they were incorrectly installed. There are much bigger problems if a 4 bolt/2 bolt connection into a concrete structure propagates a building failure. These fall arrest systems were not loaded during the...
  13. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 02

    Planters are often lined (here in houston, tx) and fail like every 1-2 decades or so- which then facilitates replacement or removal of the planters. At least in renovation/repair projects Ive been involved in.
  14. RickyTickyTavi

    Miami Beach, Champlain Towers South apartment building collapse, Part 02

    To be clear, ajk1, corrosion of the rebar is structural distress. Your top bar deterioration example may have been in a location of low negative moment or you were observing temperature steel. Rebar corrosion of flexural steel and/or shear steel will result in a reduced cross sectional area of...