Recent content by radug

  1. radug

    Grounding switches in Gas Insulated Metal Enclosed switchgear

    Hi RRaghunath, We also have a busbar grounding switch. Besides, I am not getting your point. The cable side grounding switch is farther than the CB side switch-disconnector, so it would not be able to ground the busbar. Refer to attached image. Busbar is in the top and I am referring to the...
  2. radug

    Grounding switches in Gas Insulated Metal Enclosed switchgear

    Hello, One client is requesting for the incomer of a MV gas insulated metal enclosed switchgear (arc resistant), to include two grounding switches: one in the incoming cable connection side and another one being the usual 3-position-disconnector/grounding switch that is located between the...
  3. radug

    4-20mA to 110Vac

    I know. This I explained already to Client, giving two options: either put tariff metering at Substation where we have both CT & PT of required accuracy; or pay to us to install PTs at Plant side. No success with any of the options. That is why I am asking for any experience with this PT...
  4. radug

    4-20mA to 110Vac

    It is for tariff metering. Client Contract clearly specified to measure current at one location and voltage at substation 5 km far. Although we have explained that this is nonsense, it is clearly specified in Contract and Client does not want to accept an addenda in contract for us to install...
  5. radug

    4-20mA to 110Vac

    Hello, I need to send the secondary 110Vac/sqrt(3)of a HV metering PT, to a remote location at around 5 km. I have found analogue to digital converters and signal transmission through fiber optic. However, for the remote end, I require also a 110Vac/sqrt(3) output, and I am only able to find...
  6. radug

    NEMA MG1 Motor frequency variation during starting

    Thank you waross. This is an industrial plant with a large genset that not only feeds motors with direct online starting but also UPS/DC system and other static loads. There is not a concern related to motor starting itself. It is a discussion with our engineering subcontractors that stick...
  7. radug

    NEMA MG1 Motor frequency variation during starting

    Hello, NEMA MG1 is specifying a maximum 5% frequency variation during normal operation and also during starting: "Medium motors shall start and accelerate to running speed a load which has a torque characteristic and an inertia value not exceeding that listed in 12.54 with the voltage and...
  8. radug

    Use of a F/B motor as F/F

    Hello, If my understanding is correct, a motor with an insulation class F with a temperature increase B has a 25ºC margin for operating continously without affecting its design life. If this is correct, one could use a motor purchased as F/B with no risk at F/F. My question is: if the rated...
  9. radug

    MV cabinets busbar earthing switch

    Thank you 7anoter4, The question is that I never saw a busbar earthing switch in MV cabinets, only earthing switches in each of the circuits.
  10. radug

    MV cabinets busbar earthing switch

    Dear all, For the design of 6.6kV cabinets, an engineering subcontractor is recommending to add a cabinet with an earthing switch so that in case that maintenance work has to be done in the cabinets, the busbars can be earthed before performing the Works. Cabinets are metalclad type and all...
  11. radug

    Cables in piping racks or in cable trays. Short-circuits

    Hello, It is a 220kV XLPE cable that will be laid in an existing rack. So they are 3 independent cables, one for each phase, that will be joined by cable cleats.
  12. radug

    Cables in piping racks or in cable trays. Short-circuits

    Good afternoon, A question has arisen among my workmates about piping racks foundations or supports sizing when carrying also for example ladder-type cable trays. Do the dynamic effects of short-circuits in cables need to be taken into account for sizing the supports? I usually only used...
  13. radug

    GSU Transformer energization

    Yes the power plant is new, it has a GT and ST. The GT has a GCB between the GTG and the corresponding GSUT, but the ST no, it is directly connected to its GSUT through an IPB, so synchronization will be done by closing a circuit-breaker that is at different voltage than the generator voltage...
  14. radug

    GSU Transformer energization

    Thank you both for your comments. A further question: once I have commissioned the transformer for the first time and checked that everything is ok following the procedures you explained, every time I open the circuit breaker, shall I have to repeat the commissioning procedure, or I can...
  15. radug

    GSU Transformer energization

    Hello, I have a ST Generator (15.75kV) connected directly to a GSU Transformer by IPBs, and then in the HV side of the GSU Transformer is a circuit-breaker (33 kV). As usually transformer manufacturers specify in their commissioning manuals that the transformer must be energized with no load...