Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by psgo

  1. psgo

    Piping alignment (slope & plumbness)

    Walk-down for installed piping inspection before hydro-test, we have a problem as follows, 1. Pipe Slope Pipe slope has been maintained in the direction specified by the slope arrow and / or work point elevation on the design drawing. If pipe slope is not indicted, but flow direction indicted...
  2. psgo

    Piping Slope & Plumbness

    Walk-down for piping inspection before hydro-test, we have a problem as follows, 1. Pipe Slope Pipe slope has been maintained in the direction specified by the slope arrow and / or work point elevation on the design drawing. If pipe slope is not indicted, but flow direction indicted only on...
  3. psgo

    WPS & PQ for HDPE welding

    Good afternoon, I am currently working on a power plant project which is being constructed to ASME B31.1. Before HDPE welding, Client request WPS, Operator Qualification Test, and Procedure Qualification Record for HDPE welding. 1. What code should be applied to Procedure qualification for...

Part and Inventory Search