Walk-down for installed piping inspection before hydro-test, we have a problem as follows,
1. Pipe Slope
Pipe slope has been maintained in the direction specified by the slope arrow and / or work point elevation on the design drawing.
If pipe slope is not indicted, but flow direction indicted...
Walk-down for piping inspection before hydro-test, we have a problem as follows,
1. Pipe Slope
Pipe slope has been maintained in the direction specified by the slope arrow and / or work point elevation on the design drawing.
If pipe slope is not indicted, but flow direction indicted only on...
Good afternoon,
I am currently working on a power plant project which is being constructed to ASME B31.1.
Before HDPE welding, Client request WPS, Operator Qualification Test, and Procedure Qualification Record for HDPE welding.
1. What code should be applied to Procedure qualification for...