HI There,
just need few advices on the above subject:
in fact we are exporting gas to shore from an offshore platform.
The pipe is 8" diameter and 100 km long subsea. the sea bed temperature is about 4oC.
the gas caracteristics at the metering kid prior to be sent to the subsea line are as...
321bvc,
which kind of field are you operating subsea or surface wellhead?
Using Meoh to prevent hydrate formatuion is also linked to temperature variation. Can you provide mor details?
we normally use Meoh to prevent Hydrate formation on our subsea installation. we inject Meoh downstrean and...
If I understand correctly the well has been shut in since 2000 whilst it was doing fine with no real problem noticeable.
You could sum up the previous well performance data, I mean pressure, temperature data, flow rates and all the condition of well flowing, gas lift if there is any, choke...
would you please be more precise.
what "prencible" stands for??
what is the purpose of your evaluation??
Is it a new well?
or an old well to be re-visit?
A lot to know before managing to help you.
thx
KK
Do not know if you want to quantify the amount of sand through your system? if its the case, one method is to divert the well through the Test Sep and manage to get the amount of sand. Another method is to simply install a sampling point downstream of the tree or the well flowline.
Then you can...
I'm trying to grapp some info to design an Horizontal Sep.with fluid specifications below:
separate 5000m3/d of crud at 10bars 20C.
Have been looking for more technics every where and I can not get enough methods to start my studies.
Would any one give some guidance on some useful info I ca can...
Gents,
I'm trying to grapp some info to design an Horizontal Sep.with fluid specifications below:
separate 5000m3/d of crud at 10bars 20C.
Have been looking for more technics every where and I can not get enough methods to start my studies.
Would any one give some guidance on some useful info I...
Gents,
Could any one advise a method to calculate the time depressurise a Gas line with following details:
1- Length = 65616.6 ft
2- inside Diameter (ID) = 10"
3- Pipe pressure =1200psa
4- Temp 60oF
we need to depressurise the line before starting some works on the system.
Thanks
KOKA11
COKA,
I appreciate very much such a suggestion, I think I will be planning all these stated as advices and I do beleive I will come back with satisfactory.
Thanks Coka
KOKA11
Great DrillerNic, we are going to clean it and then come back on production. The thing is the BHP of all wells are monitor by Gas lift and we do believe that a correct Gas lift optimisation must be performed to check the efficiency of wells management. thsi may reduced the incoming sand.
Internally I used to be congratulated frequently by my bosses, for my Job. they rely on every thing I undertake. But for me I can do more than what I'm cuurently doing. So I'm not really satisfied for my performance.
I'm a junior production Engineer (1 year experience in Oil field) and I still looking for new things every time and how to improve and master my Job. But People congratulate me for my Job, which I do not think is so best. What to do?