Recent content by nyclow2

  1. nyclow2

    Planning Units

    I managed to copy the schedule from one project to another. However, it did not solve my problem. While in the copy window generated from tools, project utilities, under "To" i changed the planning units to days from hours on the from/ original. However everything is still displayed in hours...
  2. nyclow2

    Planning Units

    I have been trying to change the 'planning units' in Primavera 3.1 from hours to days. However whenever I try to change or copy from another project via the menus: tools, project utilities, copy, I consistently get a message "invalid project name", eventhough all names and characters match. I...