To all, thanks for the info. To update you on what happened, the contractor cored the footings and had the cylinders broke. The hurdle was 80% at 14 days. Now the CSA allows the concrete to be deemed acceptable if f'c is within 85% at the 28 day break, etc, etc. Therefore, design f'c = 25...