Would there be an issue with installing a new zig zag grounding transformer at an existing building 480/277 3 phase, 4 wire service? In order to obtain effectively grounded solar inverter to meet utility requirement, they are requiring a grounding transformer. It seems that having a connection...
Just Curious anyone's opinion in regard to FT switches for Relay output contacts for close permissives and trip circuits for breakers. I have noticed some Switchgear manufacturers provide an FT switch on both sides of the relay output contact, and other manufacturers provide an FT switch on...
If one has an open conductor fault on a medium voltage single phase overhead circuit (phase to neutral), then have a question;
Is the fault current or voltage level different between the two scenarios below where the circuit above feeds a single phase transformer with a 120/240 volt 3 wire...
finding typical X/R ratios for standard transformers is pretty easy to find, however, I cannot find any information on a typical autotransformer X/R ratio. Only data I can find is from a Siemens PSSE model report on a project with an autotransformer that claims the impedance (per unit) is 0 +...
Does anyone have a list of the aluminimum tubing manufacturers for substations in the U.S. market? I cannot seem to find any good information on manufacturing suppliers and technical specifications with google.
How should a surge arrestor be rated on an overhead 12kV, 4 wire grounded neutral system that drops the neutral halfway along the circuit and becomes 3 wire. Would it still be considered solidly grounded system at the end of the 3 wire line, or sized like it's ungrounded?
The application is for an interconnect breaker for distributed generation. The utility is requiring the relay failure alarm contact to trip the interconnect breaker.
Given Loss of voltage to the power supply will not cause the ALARM bit to assert, I would think, therefore, that one could...
If the SEL-351 fails, the ALARM output contact goes to 1. Is there any condition of failure where the ALARM relay word bit would not go to 1 as well?
I.E. instead of wiring the ALARM output contacts of the SEL-351 into the trip coil of the circuit breaker (relay failure would trip the...
In order to minimize voltage drop, I want to start various motors in multiple steps.
Step 1: the largest motor will be started under no load (mechanical load will be zero).
Step 2: the second step will start the smaller motors, under full mechanical load.
Step 3: The last step will connect...
I applied to sit for the New York P.E. test and was accepted first try. My boss applied for the New York P.E. license through reciprocity and was rejected even though he had been a registered P.E. in pennsylvaniafor 30 years!! He was finally accepeted when he wrote several more pages...
Does anyone know how NFPA 20 is adopted in New Jersey? Is it adopted via reference in the New Jersey fire code? And if so, is it adopted in its entirety or just specific sections that are referenced in the NJ fire code?
What IBC building classification would a pump building be? The building will contain a fire pump, water booster pumps and sewage pumps and will only be occupied when maintenance is required on the pumps.