Thanks to everyone for the answers.
77JQX: What I tried to say in case 3 was to put as the elevation of the node with negative demand the "real elevation" plus an extra elevation to represent pressure.
Fake Reservoir (I've read it also as silly reservoir) is when you put a reservoir with same...
Hi Everyone,
I have some doubts about what is the best way to model water wells in an epanet network.
I have seen them modeled in many ways that I will enumerate below:
Reservoir + pipe + FCV
Reservoir in dynamic level + pipe + pump
Junction with total head and negative demand (you need a...