Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by mperr97

  1. mperr97

    Rounding Problem with Actual Work Column

    I added three columns in Microsoft Project 2000: 1.) work 2.) actual work 3.) remaining work When I place the actual hours worked, Project rounds the numbers. For instance I place 262 actual hours and when I go to the next line, Project takes the 262 and changes it to 262.08. Is there a...
  2. mperr97

    Microsoft Project 2000 - Days not translating correctly!!

    That helped thanks for answering me. One more question, I added three columns: 1.) work 2.) actual work 3.) remaining work When I place the actual hours worked, Project rounds the numbers. For instance I place 262 actual hours and when I go to the next line, Project takes the 262 and...
  3. mperr97

    Microsoft Project 2000 - Days not translating correctly!!

    I just starting using Microsoft Project 2000, I have a project plan and need to include baseline hours, estimated hours, and actual hours on a project. Is there a way to do all of this and still only calculate the actual number of hours worked? I entered all of my information into Project...

Part and Inventory Search