I added three columns in Microsoft Project 2000:
1.) work
2.) actual work
3.) remaining work
When I place the actual hours worked, Project rounds the numbers. For instance I place 262 actual hours and when I go to the next line, Project takes the 262 and changes it to 262.08. Is there a...
That helped thanks for answering me.
One more question, I added three columns:
1.) work
2.) actual work
3.) remaining work
When I place the actual hours worked, Project rounds the numbers. For instance I place 262 actual hours and when I go to the next line, Project takes the 262 and...
I just starting using Microsoft Project 2000, I have a project plan and need to include baseline hours, estimated hours, and actual hours on a project. Is there a way to do all of this and still only calculate the actual number of hours worked?
I entered all of my information into Project...