There are two methods of installation of stone columns by vibroflats:-
Wet method (Top feed)
Dry method (Bottom feed)
Is it possible to go for wet method with Bottom feed vibrofloats
For a 80 m dia oil tank, we are proposing a sand pad foundation with stone columns.
we are proposing a layer of geogrid in the sand pad foundation. what should be the layers in which the geogrid should be laid. i.e sand or aggergate.
should we lay the geogrid on the aggregate base and top up...
For a tank (Dia 80metre) foundation project
We are proposing a geogrid layer on a stone blanket with sand layer on top of the geogrid. Should it be vice versa?